Solar carport increases power capacity for automotive manufacturer
Actemium UK delivered £2 million of electrical contracting works for a solar carport project at a leading automotive manufacturing site in Northampton. Working for Centrica, Actemium provided the high-voltage (HV) and low-voltage (LV) infrastructure needed to integrate solar photovoltaic (PV) generation into the site's existing power network. The installation helped overcome grid capacity constraints by generating renewable electricity on-site, supporting growing operational demands, reducing energy costs and contributing to the manufacturer's long-term decarbonisation objectives.

Project summary:
- Sector: Automotive
- Client: Centrica
- End User: Major Automotive Manufacturer
- Location: Northampton, United Kingdom
- Expertise: HV and LV Electrical Contracting | Power Distribution | Electrical Installation and Commissioning
Project at a glance:
- £2 million electrical contracting project
- 18 months of coordinated project delivery
- 4,000 solar panels installed
- 1,500 parking spaces covered across two car parks
- 2MW renewable generation capacity supporting the site’s net-zero ambitions
The challenge: Overcoming grid capacity contraints
A leading high performance automotive manufacturer needed additional electricity to support growing operational demands. However, the site had reached the maximum capacity available from its grid connection, limiting opportunities for expansion.
With additional grid supply constrained, the manufacturer needed an alternative solution that could provide more power while reducing energy costs and supporting its carbon reduction ambitions.
A solar carport was identified as an effective way to generate renewable electricity using existing parking areas.
The project also presented complex engineering challenges. Construction on former landfill ground required specialist foundation and structural solutions, while the new electrical infrastructure needed to integrate safely with the site’s existing power network.
The Solution: Integrating solar carport generation into the existing power network
Following a competitive tender process, Actemium Birmingham, part of Actemium UK, was appointed to deliver the electrical infrastructure supporting the solar carport installation.
With approximately 15 years of experience working at the site, Actemium brought valuable knowledge of the manufacturer’s electrical systems and operational requirements.
Working from the customer-provided design and alongside specialist delivery partners, Actemium’s scope included:
- HV and LV electrical installations to support the solar PV system.
- Power distribution and switchgear to manage electricity generated by the carport.
- Electrical cabling infrastructure connecting the new installation to the existing network.
- Solar PV integration to enable renewable electricity to be used across the site.
- Testing and commissioning to support safe, reliable operation.
Combining established electrical engineering expertise with specialist solar PV capabilities enabled Actemium to deliver the infrastructure required to support the manufacturer’s long-term energy needs.
Project delivery: Coordinating specialist engineering
Delivered over 18 months, the project required close collaboration between electrical, civil, structural and solar PV installation teams.
The former landfill site presented challenging ground conditions, requiring specialist foundations before the supporting canopies and solar panels could be installed.
Actemium coordinated its electrical works around these activities, managing HV and LV installations, equipment connections and integration with the existing power network.
Challenging winter weather and evolving site conditions required flexible resource planning and careful programme management to maintain progress.
As one of Actemium Birmingham’s first large-scale solar PV projects, the scheme also strengthened its renewable energy capabilities through collaboration and knowledge sharing with experienced specialist contractors.
Results and benefits: Increasing energy capacity and reducing costs
The completed solar carport provides a new source of renewable electricity, helping the manufacturer address energy constraints while delivering long-term operational and financial value.
For Centrica
- Coordinated delivery: Collaboration across specialist disciplines supported the installation and integration of the solar PV system.
- Technical assurance: Experienced electrical engineers managed the connection to the existing power network.
- Trusted expertise: Actemium’s established site knowledge helped manage technical requirements and project interfaces.
For the automotive manufacturer
- Increased power availability: On-site solar generation provided additional electricity to support growing operational demands.
- Reduced energy costs: Renewable electricity generation reduced reliance on purchased grid power, helping lower operating costs.
- Long-term financial value: An estimated eight-year payback demonstrated the return on investment for the end client.
- Future readiness: Additional on-site generation supported future manufacturing requirements and energy resilience.
- Optimised use of space: The solar carport transformed existing parking areas into productive, energy-generating assets.
- Reduced carbon emissions: On-site renewable generation supported Scope 2 emissions reduction objectives and long-term decarbonisation ambitions.
Solar carport and renewable energy expertise from Actemium UK
From solar carport installations and PV integration to HV and LV power distribution, Actemium UK delivers bespoke engineering solutions that help industrial customers improve operational resilience, prepare for future energy demands and accelerate decarbonisation.
Our expertise spans technical advice, electrical installation, commissioning and ongoing support, providing dependable solutions built around customers’ operational requirements.