References

  • Alstom – Turbine Hall EPR Flamanville
  • EDF-FL3
  • TVO – Olkiluoto

 

Alstom - Turbine Hall EPR Flamanville
 

flamanville nuclear actemium

Calender: 2010-2016

Electrical installation within the machinery hall.

Scope of works:

-Supply and installation of 20 km – cable management systems

-Supply and installation of 200 km of MV LV & ELV power and instrumentation cables

-Installation and termination of 150 cabinets and junction boxes.

 
EDF-FL3
 

EDF-FL3 nuclear actemium

HVAC of the pumping station, tunnels and discharges structure.

52 month project, 29 months engineering & qualification period

23 months assembly & test

Scope of works:

-Engineering

-Design of the installation(heat transfer, execution drawings, seismic calculations of networks)

-Qualifications

-Assembly, tests, commissioning

 
TVO- Olikiluto
 

olkiluoto nuclear actemium

Actemium has erected the EI&C systems in the turbine hall, pumping stations and auxiliary boiler.

180,000 hours are expended up to completion.

Scope of works:

-Earthing

-Transformer erection including oil filling

-Construction of cable routes including welding

-Medium and low voltage cabling

-Instrument erection including pressure pipes

 
&nbp;