Introduction

Jaguar XJ - Final Assembly

Full electrical refurbishment of redundant 20,000 sq.m. industrial building on the Jaguar Castle Bromwich site. Relocation and installation of Jaguar XJ / Daimler trim and final assembly line from Browns Lane, Coventry.

Electrical connections to pre-assembly systems, application equipment for seals, material handling equipment, glazing assembly systems, interior trim equipment, powertrain / chassis pre-assembly lines for power train, joining and screwing stations, wheel and tank assembly.

The implemented solution...
Design, installation and testing of:

  • High voltage network
  • Electrical distribution
  • Control panels
  • High bay lighting
  • General power
  • Task lighting
  • Data network connections to process equipment
A team of up to 75 engineers delivered this project to the Customer's satisfaction in a significantly reduced timescale (12 weeks from original 24 week programme).